New Updated Loadshedding Schedule Effective From 11th Paush i.e. 26th December By Nepal Electricity Authority (NEA)

Water levels in the rivers of Nepal are getting low in the winter season so, Nepal Electricity Authority(NEA) has increased the hours of load shedding. The load shedding has now increased to 12 hours a day. Here's the new load shedding schedule.

Or if you want to download the full schedule with groups then  CLICK HERE

Loadshedding Schedule For Hetauda-Birgunj

Group / DaysSundayMondayTuesdayWednesdayThursdayFridaySaturday
Birgunj
Circuit - 1
04:00-07:00
17:00-00:20
07:00-10:00
20:00-23:00
04:00-07:00
17:00-20:00
07:00-10:00
20:00-23:00
04:00-07:00
17:00-20:00
07:00-10:00
20:00-23:00
04:00-07:00
17:00-20:00
Birgunj
Circuit - 2
07:00-10:00
20:00-23:00
04:00-07:00
17:00-00:20
07:00-10:00
20:00-23:00
04:00-07:00
17:00-00:20
07:00-10:00
20:00-23:00
04:00-07:00
17:00-00:20
07:00-10:00
20:00-23:00